Gas supply from the LNG terminal at Moheshkhali has resumed after a recent six-hour disruption caused by a technical fault, offering relief to consumers already facing low pressure amid a broader energy squeeze.

Officials said the floating storage and regasification unit (FSRU), operated by Excelerate Energy, went offline, halting regasified LNG (RLNG) supply to the national grid.

The fault was repaired later, allowing gas supply to resume, according to a statement from Petrobangla.

The temporary shutdown had led to a drop of roughly 400 million cubic feet per day (mmcfd) in gas supply, worsening pressure in areas under Titas Gas Transmission and Distribution Company Limited, including parts of Dhaka and key industrial belts.