Bangladesh has to provide more than Tk 60 in subsidies for every cubic meter of gas when imported liquefied natural gas costs $20 per million British thermal units, placing further pressure on public finances, according to a report by the Institute for Energy Economics and Financial Analysis.

The report, titled LNG-to-Power in Emerging Asia: A Five-Year Review of Project Outcomes, was released recently. It examines LNG-related projects in Bangladesh, the Philippines, Vietnam and Thailand over the past five years.

IEEFA reviewed 92 proposed LNG-fired power projects worth $109.2 billion and 44 import terminals valued at $21 billion across the four countries.

Of these, 49 power plants and 22 regasification terminals, worth a combined $67.8 billion, were cancelled or made no notable progress between 2021 and 2026.

Only 11 per cent of the proposed power generation capacity and 15 per cent of the planned terminal capacity came online. Completed power plants took more than seven years on average to start commercial operation, against the three to four years typically projected by developers.

The report attributed the projects’ weakened viability and difficulties in securing financing to volatile LNG prices, higher capital costs, longer delivery times for gas turbines and the depreciation of Asian currencies against the US dollar.