9th May 2024
EP Report

Although Matarbari Coal-fired Power Plant has been supplying electricity to the national grid since the commissioning of its first unit in December 2023, it has not received any payment from the Bangladesh Power Development Board (BPDB).

 

“We’ve so far not received any payment against our supply of electricity to the national grid," said Abul Kalam Azad, managing director of the Coal Power Generation Company Bangladesh Limited (CPGCBL).

 

The CPGCBL, a state-owned company of the government, set up the Matarbari coal-fired plant with ultra-critical technology under the financing of the Japan International Cooperation Agency ((JICA).

 

The 1200-MW power plant, having two units each with 600 MW capacity, is on 1,414 acres of land in Matarbari and Dhalghata unions of Maheshkhali upazila of Cox's Bazar district.

 

A deep-sea project was developed to facilitate coal unloading from ships. The first unit of the Matarbari Coal-Fired Power Plant was synchronized with the national grid in July of this year.