Project deadline extended by 2 years, but authorities hope to complete grid line work before scheduled commissioning

 

One of the two units of the Rooppur Nuclear Power Plant will be commissioned this December if transmission lines are ready although the deadline for the project's completion has been extended to 2027.

 

The decision to extend the deadline by two years was made at a meeting between Russian and Bangladeshi officials in Dhaka in the second week of February.

 

Officials, however, said no specific date for the project's completion has been fixed yet.

 

The 2400MW power plant is being built in Rooppur, Pabna, at a cost of $12.65 billion. Of the amount, $11.38 billion will be provided by Russia as soft loans. It is the most expensive development project in the country ever.