9th May 2018

(Dhaka) May 09, 2018: Summit, the largest Independent Power Producer (IPP) in Bangladesh has completed construction of another HFO fueled reciprocating power plant with 300 MW capacity. The Summit Gazipur II Power Limited has begun supplying power to the national grid from 5th May 2018. It was implemented as a fast-track project within nine months, a period that was set by Bangladesh Power Development Board (BPDB) and Power Division of the Ministry of Power, Energy and Mineral Resources.

The Letter of Intent (LoI) of this project was issued on 10th August 2017 and only within nine months since then on 9th May 2018, Wednesday the ‘100 Hour Reliability Run Test’ as well as ‘Dependable Capacity Test’ were completed.