7th June 2018
EP Desk

 

Sembcorp Marine has completed three integrated fixed platform topsides the Total-operated high-pressure/high-temperature (HP/HT) Culzean gas field in the UK central North Sea.

 

The wellhead, utilities and living quarters, and central processing facility topsides were constructed at the Sembcorp Marine Admiralty Yard over 32 months.

 

The approximately 30,000-metric tons integrated topsides will handle up to 500 MMscf/d of gas and 25,000 b/d of condensate.

 

The wellhead platform and central processing facility left Singapore for the Culzean field in early May; the utilities and living quarters is expected to leave soon.

 

In addition, a power generation module and two interconnecting bridges, which form part of the integrated topsides, were separately completed at Sembcorp Marine subsidiary Sembmarine SLP in Lowestoft, UK, for delivery in June.

  